Project 2013-尝试在项目中移动任务并让它尊重新的前任而不是旧的前任
好的,我正在制定一个相当大的项目时间表。
Ok, I am working on a rather large project schedule.
在升级到Project 2013之前,该文件已在Project 2007中使用。
Before having to upgrade to Project 2013, the file was used in Project 2007.
基本上我在移动任务时遇到问题只是为了让他们仍然尊重旧的前任而不仅仅是新的。
Basically I am having a problem with moving tasks only to have them still respect their old predecessor instead of just the new one.
基本上我有4个任务(开始时)日期):任务A:月份的第1天,任务B:月份的第5天,任务C:月份的第9个月,任务D:月份的第13个月。
Basically I have 4 tasks ( with start dates): Task A: 1st of month, Task B: 5th of month, Task C: 9th of month, Task D: 13th of month.
我想移动说任务D任务B前面,它是A / 1,D / 5th,B / 9th,C / 13th。但所有发生的事情都是任务改变顺序,但所有日期都保留在原始任务中。这不是Project 2013之前的问题。
I would want to move say Task D infront of Task B and have it go A/1st, D/5th, B/9th, C/13th. But all that happens is that the tasks change order but all the dates remain with their original tasks. This wasn't a problem before Project 2013.
除了我每次制作时都要解除链接和重新链接之外是否有任何解决方法?更改?
Is there any fix for this outside of having to unlink and relink every time I make change?
您可以在列表中上下移动任务并仍然保留前任和后续任务的事实之一MSP的神奇功能,它一直如此。
The fact that you can move tasks up and down in the list and still preserve the predecessors and successors is one of the fabulous features of MSP, and it always has been so.
如果您对任务施加了SNET日期限制,使其不早于这些日期,那么您不需要前任所有。日期限制和前任/后继者的混合几乎肯定会引起冲突。
If you have imposed SNET date constraints on the tasks to make them happen no earlier than those dates, you don't need predecessors at all. A mixture of date constraints and predecessors/successors is almost certain to cause conflicts.