将项目开始日期更改为更晚,但不更新任务日期
我有一个尚未启动的新项目的新项目文件。它还没有实际意义。大约有1,000个任务,并且只有大约10-15个具有除"尽快"之外的约束。由于客户的延误(你听说我们联邦政府关闭了那么多的b $ b b),项目启动时间已经延迟了。
I have a new Project file for a new project that hasn't started. It has no actuals yet. There are about 1,000 tasks, and only about 10-15 have a constraint other than "soon as possible." Due to a delay by the customer (you heard about that little federal government shutdown we had?) the project start has been delayed.
我更新了项目开始日期(项目,项目信息,开始日期),使其在27个工作日后完成。但是,项目中没有其他日期发生变化。我期待没有约束和没有前任的任务将在新项目开始日期更新为
,但它们仍然从旧日期开始。
I updated the Project Start date (Project, Project Information, Start Date) to make it 27 working days later. However, no other dates in the project have changed. I was expecting that the tasks with no constraints and no predecessors would be updated to start on the new project start date, but they still start on the old date.
我做不希望开始在初始任务上添加约束只是为了将它们推向右边同步到项目开始日期。如何强制不受限制的任务在新项目开始日期开始?
I do not want to start adding constraints on the initial tasks just to push them to the right to synch to the project start date. How can I force unconstrained tasks to start on the new project start date?
让世界变得更好,一次一个烦恼
Making the world a better place one fret at a time
六个字符串,
首先,您使用的是哪个版本的Project?是否使用最新的Service Pack进行了更新?
First of all, which version of Project are you using? Is it updated with the latest service pack?
转到文件/选项/计划组。是否可以选择"自动安排的任务"。设置为项目开始日期还是设置为当前日期?如果是后者,请改变它。这样可以解决吗?
Go to File/Options/Schedule group. Is the option for "auto scheduled tasks scheduled on" set for Project Start Date or it it set for Current Date? If the latter, change it. Does that fix it?